Long-term maintenance plans for body corporates

Every body corporate has the same awkward truth to manage: buildings wear out on a timetable, and money arrives in small annual instalments. Roofs, membranes, lifts, painting and cladding repairs are all predictable in a general sense and unpredictable in the detail. The long-term maintenance plan, usually shortened to LTMP, is the legal tool for bridging the gap between the two.

What the law requires

Section 116 of the Unit Titles Act 2010 says a body corporate must establish and regularly maintain a long-term maintenance plan. The plan must cover at least ten years from its date or its last review. Its purposes, according to the Act, are to identify future maintenance and estimate the costs, to support the funds, to provide a basis for levying owners, and to guide the annual maintenance decisions the body corporate makes.

A set of changes that took effect on 9 May 2024 added detail. The government's Unit Title Services site describes a two-tier approach:

Templates for both a simple plan and a complex one are published on the Unit Title Services site.

The fund that pays for it

A body corporate must set up a long-term maintenance fund unless it decides by special resolution not to. If it takes that decision, it has to review it every year and may later choose to start a fund. The money can only be spent on items in the plan. Importantly, the body corporate decides how much to hold, and the fund does not need to cover everything the plan anticipates.

Other funds are optional: a contingency fund for unbudgeted spending, and a capital improvement fund for upgrades not provided for in the plan. The Act spreads the cost among owners through levies. The operating account, the long-term maintenance fund and any contingency fund are levied in proportion to each owner's utility interest, while a capital improvement fund is levied by ownership interest.

There is a control on overspending. If the amount to be spent on a single maintenance item goes more than 10 per cent above what the plan allowed, the body corporate needs a special resolution to approve it. A special resolution needs 75 per cent of votes cast.

What the plan means for buyers

The plan matters beyond the committee room. An owner selling a unit must give the buyer a pre-contract disclosure statement that includes a copy of the plan, its next review date, any maintenance the body corporate proposes to carry out in the coming year and how it will be paid for, and works under the plan due to begin within three years with their estimated costs. The Ministry's page on the 2022 amendments adds that the plan and its next review date must also appear in pre-settlement statements, and that records must be kept for three years in case the regulator asks for them.

A plan that is out of date, with a long list of items marked "to be determined", or a fund balance far below the plan's projected spending tells a buyer to expect higher levies or a special levy later.

Questions a committee can ask of its own plan

  1. When was it last reviewed? For large developments the review is a three-year obligation.
  2. Who prepared it? A building professional's input is required for large bodies corporate unless owners vote otherwise.
  3. Does it cover everything? Check for roofs, balconies and decks, waterproofing, cladding, lifts, fire systems, painting, car park surfaces, plant and shared pipework.
  4. Does the funding add up? Compare the plan's projected spending with the current fund balance and the annual contribution.
  5. What condition information supports the costs? Inspection reports on particular elements make an estimate more convincing.

For timber elements, a specialist report can feed directly into the plan. Some committees commission borer inspections for body corporates on older timber buildings so that any treatment or repair work appears in the budget before it becomes urgent. That is an example of the kind of condition evidence that helps a plan show realistic costs rather than guesses.

Keeping owners on side

A plan only works if owners fund it. Because levies set the fund, the AGM is the place to explain the maths. Many committees find it easier to present a plan as a short schedule: the item, when it is expected, what it will cost, and how much of the fund is already set aside. The committee should also say what happens if the fund is short, whether by raising levies over time or by a special levy.

If a building has timber elements that have never been inspected, the committee can approach a firm such as Lignum Timber Inspections and ask what an inspection would cover, how findings would be reported, and whether the report could be attached to the plan as supporting evidence.